Search by SSID Option
The Search by SSID Report details a student’s test opportunities and the status of those test opportunities. It can be generated by selecting the Search by SSID option from either the Home Page Dashboard screen (indicated in figure 1) or the Test Progress Reports drop-down list.

Figure 1. Search by SSID option in the Test Progress Reports drop-down list
Users have the option of entering SSIDs manually or uploading a single-column spreadsheet with the SSIDs to be reported.
Step 1. Enter SSID(s)
The “Enter SSID(s)” section of the Search by SSID screen, shown in figure 2, provides the field used to generate the test completion rates for a specific assessment. The default means of entry is entering SSIDs in the Student ID(s) field (the Enter radio button).

Figure 2. Enter SSID(s) options on the Search by SSID screen
A user can either enter SSID(s) into the Student ID(s) field, using a comma to separate multiple SSIDs; or take the following steps to upload up to 1,000 SSIDs from an Excel spreadsheet or CSV file:
-
Select the Upload radio button above the “Enter SSID(s)” section (indicated in figure 3).

Figure 3. Upload SSID options on the Search by SSID screen
- Select the [Choose Files] button and then follow the prompts to select an Excel spreadsheet or CSV file, with students’ SSIDs listed in a single column, for upload.
Step 2. Generate the Report
Refer to the Column Definitions subsection in the Plan and Manage Testing, Search by SSID, and Progress Summary Reports section for a description of the columns in the on-screen and Excel or CSV reports.
Generate the report by selecting the [Generate Report] button (figure 4). This will create an on-screen report.

Figure 4. [Generate Report] button